| Environmental Compliance and Consultation Review |
A: 165. Environmental Compliance and Consultation Review |
|
06/30/2028 |
|
| Effective implementation management and timely contract administration |
B: 119. Routine/daily administration of work elements |
|
06/30/2028 |
|
| Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish |
C: 114. Lower Clearwater/Potlatch Project Identification |
|
06/30/2028 |
|
| Attend Potlatch Implementation Group and subcommittee meetings. |
D: 191. Watershed Coordination |
|
06/30/2028 |
|
| Complete restoration on Sharrock-Becker properties on Big Meadow Creek. |
E: 29. IDFG: Sharrock-Becker Big Meadow Creek - habitat enhancement project implementation |
|
07/31/2027 |
|
| Develop and submit completed 100% design plans. |
F: 175. IDFG: Spring Valley Creek Flow Augmentation - Design |
|
06/30/2027 |
|
| Final design complete |
G: 175. IDFG: West Fork Little Bear Creek #3 - Design and engineering |
|
06/30/2027 |
|
| Develop and submit completed 100% design plans. |
H: 175. IDFG: State Highway 8 Big Meadow Creek Culvert Replacement - Design |
|
06/30/2028 |
|
| Distribute outreach videos and blogs. |
I: 99. IDFG: Outreach and Education |
|
06/30/2028 |
|
| Complete unscheduled maintenance/repairs as needed and adhere to environmental compliance requirements. |
J: 186. IDFG: Unscheduled maintenance & repair |
|
06/30/2028 |
|
| Develop and submit completed 100% design plans |
K: 175. TU: Upper Clear Creek AOPs Design and Engineering |
|
06/30/2027 |
|
| Remove knotweed on 2.5 acres |
L: 199. TU: Clear Creek Knotweed Treatment on McLean Property - Preconstruction |
|
06/30/2027 |
|
| Orofino Creek Fish Passage Analysis complete |
M: 115. TU: Orofino Creek Fish Passage Analysis |
|
06/30/2028 |
|
| Produce accessible, error-checked datasets |
N: 157. TU: Orofino Creek Genetic Assessment |
|
06/30/2028 |
|
| Completed Progress (Annual) Report |
O: 132. IDFG: Annual report for Contract 84063 Rel 21 (July 1, 2026-June 30, 2027). |
|
03/31/2027 |
|
| Completed Progress (Annual) Report |
P: 132. IDFG: Submit Progress Report for the period Jul 2027 to June 2028 |
|
06/30/2028 |
|
| Completed Progress (Annual) Report |
Q: 132. TU Submit Progress Report for 84063 Rel 21 (Jul 2026-June 2027) |
|
06/30/2027 |
|
| Completed Progress (Annual) Report |
R: 132. TU: Submit Progress Report for the period Jul 2027 to June 2028 |
|
06/30/2028 |
|