| Effective implementation management and timely contract administration |
B: 119. RC&D management of the YTAHP program & subcontractor administrative work |
|
03/31/2027 |
|
| Watershed coordination activities have been completed. |
C: 191. Watershed Coordination |
|
03/31/2027 |
|
| Completed Progress (Annual) Report |
D: 132. Submit annual report for 04/01/2025 - 03/31/2026 (FY 2025) |
|
09/01/2026 |
|
| Technical input into project development |
E: 122. Technical Review |
|
03/31/2027 |
|
| Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish |
F: 114. Identify and Select projects |
|
08/01/2026 |
|
| Produce Environmental Documentation |
G: 165. Produce Environmental Compliance Documentation - Permitting |
|
03/31/2027 |
|
| Trees and shrubs are planted |
H: 47. Wenas Creek RM 10.0- South Fork Wenas Riparian Restoration- Plant Vegetation |
|
01/01/2027 |
|
| Vegetation Maintenance is complete. |
I: 198. Naches River RM 10.0 - Edgar Riparian Protection and Enhancement- Phase 2- Maintain Vegetation (Continued from WE I on Contract 96660) |
|
03/31/2027 |
|
| Fish screen is installed |
J: 208. Wenas Creek RM 12.0- Cameron Ranch- Fish Screen (New) |
|
01/01/2027 |
|
| Fish screen is installed |
K: 208. Rattlesnake Creek RM .37- Fish Screen (New) |
|
01/01/2027 |
|
| Permit-ready designs have been completed |
L: 175. Wenas Creek RM 12.0- Lazy Heart Fish Screen and Passage- Produce Design (Connected to WE L on Contract 96660) |
|
03/31/2027 |
|
| Preferred alternative (typically 30%) completed |
M: 175. Wenas Creek RM 11.0 - Haas Fish Screening and Passage- Produce Design (Continued from WE M on Contract 96660) |
|
03/31/2027 |
|
| Complete 80% Project Designs |
N: 175. Coleman Creek RM 5.4 - Raap (continued from WE N in 2024 Contract 96660) |
|
03/31/2027 |
|
| Complete Construction ready Plans and Specifications |
O: 175. Naneum Creek RM 4.7 - Ellensburg Water Company Intersection (continued from WE AB in 2025 Contract 96660) |
|
01/02/2027 |
|
| Complete Final Design and Specifications |
P: 175. Naneum Creek RM 3.75 - McCullough Rd Fish Passage (continued from WE P in 2025 Contract 96660) |
|
02/05/2027 |
|
| Complete Project Designs and Specifications |
Q: 175. Cooke 4.25 - Fish Screen and Passage (continued from WE Q in 2025 Contract 96660) |
|
03/31/2027 |
|
| Final Project Designs and Specifications |
R: 175. Cooke 3.86 - Fish Screen and Passage (continued from WE R in 2025 Contract 96660) |
|
03/31/2027 |
|
| Maintain Vegetation |
S: 198. Coleman 2.0 Vegetation Maintenance (connected to WE V in 2025 Contract 96660) |
|
03/31/2027 |
|
| Vegetation maintenance activity implemented |
T: 198. Naneum 2.9 Vegetation Maintenance (connected to WE W in 2025 Contract 96660) |
|
03/31/2027 |
|
| Vegetation maintenance activity implemented |
U: 198. Coleman Creek 4.4 (Schomer) Vegetation Maintenance (connected to WE X in 2025 Contract 96660) |
|
03/31/2027 |
|
| Planting maintained |
V: 198. Cascade at Coleman Creek (RM 5.4) (connected to WE AA in 2025 contract 96660) |
|
03/31/2027 |
|
| Correct Fish Passage Barrier |
W: 85. Naneum 3.2 Fish Passage (continued from WE Y in 2026 Contract 96660) |
|
03/31/2027 |
|
| Install fish screen and passage |
X: 208. Cooke Creek 4.25 Fish Screen and Passage (connected to WE Z in 2025 Contract 96660) |
|
03/31/2027 |
|
| Complete Installation of Siphon and Fish Screen/Passage Structure |
Y: 208. Cascade at Coleman Creek (RM 5.4) Fish Passage and Screening (connected to WE AA in 2025 Contract 96660) |
|
07/01/2026 |
|
| Fish Passage Structure Constructed and Installed or Replaced |
Z: 208. Naneum Creek RM 4.7 - Ellensburg Water Company Intersection (connected to WE AB in 2025 Contract 96660) |
|
03/31/2027 |
|
| Install Fish Passage Structure |
AA: 184. Naneum Creek RM 3.75 - McCullough Rd Fish Passage (Associated with WE P) |
|
03/31/2027 |
|
| Final Design Complete |
AB: 175. Whiskey Creek Barriers RM 1.5-1.7 (connected to WE T in contract 96660) |
|
02/04/2027 |
|
| Fish screen and fish passage structures complete |
AC: 208. Whiskey Creek Barriers RM 1.5-1.7 (connected to WE AC in contract 96660) |
|
03/31/2027 |
|