| Province | Subbasin | % |
|---|---|---|
| Columbia Cascade | Entiat | 25.00% |
| Methow | 25.00% | |
| Okanogan | 25.00% | |
| Wenatchee | 25.00% |
| Previous: | Next: |
|---|---|
| n/a |
* Expenditures data includes accruals and are based on data through 31-Mar-2026.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Documentation and assistance provided to BPA EC Lead | B: 165. Obtain Required Permits, Authorizations, and Documentation | 04/30/2027 | ||
| Effective implementation management and timely contract administration | C: 119. Manage BPA Contracting Requirements | 04/30/2027 | ||
| Maintain regular and timely communication with the UCSRB | D: 191. Coordinate with regional and local project partners | 04/30/2027 | ||
| 16" Riverscreen purchased & installed | E: 208. Lake Osoyoos pump screen | 04/30/2027 | ||
| Bear creek Test Well Feasibility | F: 115. Bear Creek technical oversight and project development | 04/30/2027 | ||
| Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish | G: 114. Libby Creek Test Well Feasibility & Out Year Planning List Development | 04/30/2027 | ||
| Beaver creek project scoping | H: 115. Beaver Creek technical oversight and project development | 04/30/2027 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered) |
|
| Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 185 | Periodic Status Reports for BPA | |||||||
| B | 165 | Obtain Required Permits, Authorizations, and Documentation | |||||||
| C | 119 | Manage BPA Contracting Requirements | |||||||
| D | 191 | Coordinate with regional and local project partners | |||||||
| E | 208 | Lake Osoyoos pump screen | |||||||
| F | 115 | Bear Creek technical oversight and project development | |||||||
| G | 114 | Libby Creek Test Well Feasibility & Out Year Planning List Development | |||||||
| H | 115 | Beaver Creek technical oversight and project development | |||||||
| I | 132 | No Report to BPA Required per COR -- Summary to UCSRB |